Qu'Appelle Boulevard Extension Project
Construction of the roadway extension of Qu’Appelle Boulevard to Rose Hill Road will take place from late 2025 to 2027.
A summary of current, past, and upcoming Capital Projects
Capital Projects are part of the City's Civic Operations and help maintain or improve municipal infrastructure.
The following is a list of active and upcoming capital projects in Kamloops, which may be viewed to learn about the scope, timelines and estimated costs related to each, as well as resident and/or expected traffic impacts (if applicable). You may also ask questions or leave comments for the project team's consideration.
For current traffic impact information, you can also view the Kammute page on our site.
Expand the following projects below.
Construction of the roadway extension of Qu’Appelle Boulevard to Rose Hill Road will take place from late 2025 to 2027.
Learn more
The Kamloops Centre for the Arts is part of the Build Kamloops vision.
Learn more
Construction of the Riverside Park outdoor skating facility will begin in spring 2025.
Learn more
Work on the Tranquille Road Sanitary Main and Road Enhancement Project | Phase 3 (Crestline to Southill) is scheduled to begin in early June 2025.
Learn more
The 4th Avenue Sewer Upgrades Project is comprised of a sanitary sewer main upgrade from Lansdowne Street to Battle Street.
Learn more
PROJECT SCOPE
The City of Kamloops has contracted DW Builders to complete restoration work at St. Andrews on the Square, returning the building to its pre-damage condition while also incorporating upgrades to improve accessibility, code compliance, and overall functionality.

This restoration work supports maintaining a tangible link to the past, anchoring Kamloops’ identity and historical continuity, while providing a useful, functional space for events and gatherings.
In May 2024, the facility–the oldest public building remaining in the city–sustained fire damage, with most of the impact limited to the exterior and attic, while the interior was primarily affected by smoke and firefighting water.
HOURS OF WORK
The work will occur Monday through Friday, from 7:00 am to 5:00 pm, from early October 2025 to February 2026.
Some evening or weekend work may be required.
PROJECT IMPACTS
Surrounding commercial and residential properties can expect noise and truck traffic.
Traffic impacts are not expected during this project.
UPDATE FOR DECEMBER 22
The majority of the project is complete. The contractor will return in the spring when conditions are suitable for planting and landscaping.
UPDATE FOR OCTOBER 7
Road closure:
Traffic pattern change:
Detours:
Pedestrians:
No parking:
Bus stop:
After hours:
PROJECT SCOPE
The City of Kamloops has contracted Extreme Excavating Ltd. to perform sewer upgrades to the existing sanitary line between Monarch Drive and Waddington Drive, adjacent to Springhill Creek. The current sanitary line is aging and does not have enough capacity to meet the current demand.

The project will also include the creation of an access road at the corner of Gleneagles Drive and Monarch Drive, removal and replanting of trees and vegetation, reseeding disturbed areas outside of the road alignment, and upgrades to the walking path.
We are advising residents that this work is scheduled to begin in early October, with expected completion in December 2025.
Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some evening and weekend work required.
TRAFFIC IMPACTS
While some work will occur in the intersection of Monarch Drive and Gleneagles Drive, overall traffic impacts during this work will be minimal.
Please obey all traffic control personnel and signage when crews are in the area.
RESIDENT IMPACTS
Work will begin at Monarch Drive and end near Waddington Drive. The bulk of of the work will occur in the greenspace near Springhill Creek.
During the work, water service disruptions may occur. Impacted residents will receive advanced notification when any planned water shutoffs are scheduled.
Throughout the construction period, vibratory compaction equipment may be in use; therefore, any fragile items should be packaged or protected from damage due to vibration.
As this project location is in close proximity to streams, riparian areas, and wildlife, the City is abiding by an Environmental Management Plan that will help mitigate and minimize the potential for adverse environmental impacts, as well as provide best practices for how best to manage the work in this area.
PEDESTRIAN IMPACTS
For safety reasons, the green space and walking trail within construction zone will be closed for the duration of the construction project. Please obey all posted signage.
UPDATE FOR DECEMBER 22
The contractor will return in January (weather permitting) to continue work.
Once the building is complete, the mechanical apparatus for the pressure-reducing station will be installed. Once that is all complete, the final water connections will be done outside the building, connecting the higher-pressure zone to the lower-pressure zone (weather permitting).
UPDATE FOR JULY 10
On Friday, July 11, paving work will occur on Hillside Drive North and McGill Road just past Bunker Road.
Expect single lane alternating traffic and frequent temporary road closures to allow the movement of paving and construction equipment. Paving is expected to begin around 8:30 am on Friday.
To avoid commuting slowdowns due to moving paving equipment and single lane alternating traffic, it is recommended commuters travel along McGill Road away from the construction zone to access Summit Drive.
UPDATE FOR MAY 21
From May 23 until June 20, construction will move into the south side of Hillside Drive North. During this time, Hillside Drive North will be single lane alternating traffic moving up to Bunker Road. Traffic control personnel will be used to guide traffic.
On Saturday, June 21, there will be a temporary road closure on McGill Road just past the Bunker Road intersection. McGill Road will be accessible for local traffic only starting at the University Drive intersection. Bunker Road will be closed and traffic will exit McGill the same way it entered.
Further, the Bunker Road Recycling and Yard Waste Depot will be temporarily closed on June 21 due to the road closure.
After June 21, please expect single lane alternating traffic along within the corridor of McGill Road and Hillside Drive North as contractors pave and restore the boulevard. This work is expected to be completed by the end of July.
Note: All dates are approximate and may change based on weather and other factors.
PROJECT SCOPE
The City of Kamloops has contracted BA Dawson Blacktop Ltd. to install a watermain extension along Hillside Drive connecting the 2088 pressure zone to the 1786 pressure zone through a pressure reducing valve station.
The result will be an upgrade to water servicing in the area and improvement of fire protection to enable development of high density residential and commercial lots.
HOURS OF WORK
We are advising impacted properties that work will begin in spring 2025, with expected completion in fall 2025.
Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some weekend work required.
IMPACTS
Throughout the project, water service disruptions may occur. Impacted properties will receive advanced notification when any planned water shutoffs are scheduled.
During construction, dust control measures will be in place, as heavy vibratory equipment will be used. Pack up fragile items to protect them from damage due to vibration. Expect heavy truck traffic and noise disruptions from construction equipment.
PROJECT UPDATE
All roadway works have been completed, with the only remaining aspect of the project being the achievement of whistle cessation. The project team is working with all partners to achieve this final milestone and will provide an update in 2026. Thank you for your patience and co-operation thus far!
UPDATE FOR AUGUST 28
Work is scheduled to recommence on Lorne Street next week. To accommodate this work, a closure and detour will be in place on 7th Avenue from Tuesday, September 2, through Saturday, September 6 while crews build, install, and weld rail panels.
Residents on 7th Avenue will continue to have access during construction, and accommodations will be made as needed.
In addition, on Saturday, September 2, traffic will be single lane alternating on Lorne Street to support the unloading of materials.
UPDATE FOR JULY 14
Acres Enterprises has demobilized from site for a brief pause until Monday, August 11.
When the project restarts, road closures will temporarily recommence while the remainder of the work is completed.
Asphalt prep, paving, and restoration, including signage installation, will begin August 14, with overall project completion expected in September.
UPDATE FOR JUNE 13
A closure is planned at 7th Avenue and Lorne Street for construction for the Lorne Street Rail Improvement project. The closure should last 3 days while the construction crew reshapes the existing subgrade around the rail track. As of now, this is scheduled for June 16-18, but is subject to change. Please continue to monitor this page for project updates.
PROJECT SCOPE
The City of Kamloops has contracted Acres Enterprises Ltd. to perform rail safety improvements at CN Rail crossings on Lorne Street to accommodate improved safety for pedestrians, cyclists, and motorists to support the future cessation of train whistles.
The project is partially grant funded by Transportation Canada’s Rail Safety Improvement Program and will include the following elements:
HOURS OF WORK
We are advising residents that work is scheduled to begin in spring 2025, with completion anticipated in fall 2025.
Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some weekend work required.
TRAFFIC IMPACTS
Traffic will be temporarily impacted within the construction zone, including road closures, detour routes, and single lane alternating traffic patterns.
Please plan accordingly and obey all signage and traffic control personnel.
RESIDENT IMPACTS
During construction, dust control measures will be in place, as heavy vibratory equipment will be used. Pack up fragile items to protect them from damage due to vibration.
Expect heavy truck traffic and noise disruptions from construction equipment.
PEDESTRIAN IMPACTS
During construction, sidewalk closures may be in effect. Please obey all signage when navigating the area.
UPDATE FOR DECEMBER 22
The contractor will return in January and will
start tunnelling under Highway 1 for the connection from Hillside Drive to
Sugarloaf Road. Simultaneously, crews will continue to work on installing the
sewer pipe in the lower section of the project. This will include blasting and
earthworks in addition to the pipe installation.
PROJECT SCOPE
The City of Kamloops has contracted Extreme Excavating to add approximately 6.4kms of 600mm diameter and 450mm diameter gravity sanitary mains from Sugarloaf Road to Mission Flats Road.
Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some evening and weekend work required, until summer 2026.
PROPERTY IMPACTS
Throughout the project, water service disruptions may occur. Impacted properties will receive advanced notification when any planned water shutoffs are scheduled.
During construction, dust control measures will be in place, as heavy vibratory equipment will be used. Pack up fragile items to protect them from damage due to vibration. Expect heavy truck traffic and noise disruptions from construction equipment.
Please note that we are only able to respond during regular City operating hours, 8:00 am–4:00 pm, Monday to Friday (excluding holidays). Any emergency issues or requests for service should be directed to 250-828-3461.
To ask a question you must create an account or log in.
These are the people that are listening and responding to your questions.
{{ question.username }} asked
| Question asked to {{ question.respondent.name }}
Category: {{ question.category }}
{{question.description}}
Have questions or want to learn more about a project, contact us below:
| Website | www.kamloops.ca |
|---|---|
| In writing | City of Kamloops, 7 Victoria Street West, Kamloops BC, V2C 1A2 |
The City of Kamloops acknowledges that we are located on Tk̓emlúps te Secwépemc territory, situated within the unceded ancestral lands of the Secwépemc Nation.
We honour and respect the people, the territory, and the land that houses our community.
This site is owned and operated by the City of Kamloops using software licensed from Social Pinpoint. We take appropriate measures to safeguard personal information and use encryption, access controls, and other security measures to protect it. For details on what personal information we may collect and access, please refer to Social Pinpoint's Privacy Policy.
Users have the right to access, correct, or delete their personal information, subject to certain exceptions. For details on how to exercise these rights, or for any questions or concerns about our privacy practices, please contact us in writing at communications@kamloops.ca.
This privacy policy may change from time to time, and any changes will be communicated to users through the site.
The following Terms and Conditions govern the use of Let's Talk Kamloops (“the site”). The software platform is owned by Social Pinpoint Pty Ltd and operated by us, the City of Kamloops.
By accessing and using this site, you are choosing to accept and comply with the Terms presented throughout this agreement as well as the Privacy Policy and Moderation Policy. These Terms apply to all visitors and users of this site. Linked sites, affiliated services or third party content or software have their own Terms that you must comply with. If you disagree with any of the Terms presented in this agreement, you may discontinue using the site immediately.
If you are under 18 years old, please ensure that your parent or guardian understands and accepts these Terms and Conditions (including the Privacy Policy and Moderation Policy).
What are the conditions with a user’s account?
While using the site, you must not violate any applicable laws and regulations. It is our duty to protect the confidentiality of content you provide on our site in accordance with our Privacy Policy. When you create an account with us, you must always provide us with accurate information. Failure to provide accurate information violates the Terms, which may result in immediate termination of your account on our service. You are responsible for protecting your own password you use for this site and for any activities done under that password. Unauthorised use of your password or account must be immediately reported to us. In some cases, we or our agents may require access to your user accounts to respond to technical issues.
We are not responsible for the content on the site that has been provided by the users of the site. Any content posted by you is subject to the rules of our Moderation Policy. Your contribution to the site may be edited, removed or not published if we consider it inappropriate (refer to Moderation Policy). Contributors should also be aware that their posts may remain online indefinitely. Where practical, you may choose not to identify yourself, deal with us on an anonymous basis or use a pseudonym.
What do we require from our users?
You must understand and agree that, without limitation:
Can your account be suspended or terminated?
We may terminate or suspend access to your site and/or account immediately, without prior notice, including without limitation if you breach the Terms. We may immediately deactivate or delete your account and all the related files and information in your account. After your account has been terminated, the content you have posted may also remain indefinitely on the site.
If you want to terminate your own account, please send an email to communications@kamloops.ca.
Governing Law
These Terms shall be governed in accordance with the laws of the Province of British Columbia, Canada, without regard to its conflict of law provisions.
Indemnification
The City of Kamloops, its subsidiaries, affiliates, officers, agents, licensors and other partners are not responsible for any loss, liability, claim, or demand, including legal fees, made by any third party due to or arising from a breach of this agreement and/or any breach of your representations and warranties set forth above.
What content do we own?
This website contains the copyrighted material, trademarks, patents, trade secrets and other proprietary information (“Intellectual Property”) of the City of Kamloops and its suppliers and licensors. The City of Kamloops owns and retains all proprietary rights in the intellectual property. All intellectual property in the content of this site including without limitation to text, software, source code, pages, documents and online graphics, photographs, sounds, audio, video and other interactive features are owned by or licensed to us.
Any original content that you submit or post on our site may be made available to the public and allows users to share your content (with the end user acknowledging your contribution) under the Creative Commons Attribution-ShareAlike 4.0 License.
Except for Intellectual Property which is in the public domain or for which you have been given written permission, you may not copy, alter, transmit, sell, distribute any of the Intellectual Property on this site.
We are not responsible for your communications or dealings, including payment and delivery of goods or services, with a third party found via our website. Any loss or damage incurred from those communications or dealings are solely between the user and the third party.
Disclaimer and Warranties
Users must agree that you use of the site is at your own risk. We make no warranty that the site will meet your requirements or be uninterrupted or error-free. Any material that the user downloads through the site is done at their own risk and are responsible for any damages to their computer system or loss of data.
What happens if these Terms change?
We reserve the right, at our sole discretion, to modify or replace these Terms at any time without notice. The most recent version of the Terms can be seen on this page. By continuing to access or use our site after those revisions become effective, you agree and will comply to the revised terms. If you do not agree to the revised terms, please discontinue using our site.
Contact Us
If you have any questions about these Terms, please contact us at communications@kamloops.ca.
Enter your email address below. We will send you instructions to reset your password.
Back to Log in
Creating an account helps us better understand your needs and the needs of the community.
Already have an account? Log in now
Thank you, your account has been created.
Completing the questions below helps us better understand the diverse range of people who contribute their ideas. The questions are optional.
You’re using an outdated browser.
Some features of this website may not work correctly. To get a better experience we strongly recommend you download a new browser for free: