Skip to main content

Capital Projects are part of the City's Civic Operations and help maintain or improve municipal infrastructure.

The following is a list of active and upcoming capital projects in Kamloops, which may be viewed to learn about the scope, timelines and estimated costs related to each, as well as resident and/or expected traffic impacts (if applicable). You may also ask questions or leave comments for the project team's consideration.

For current traffic impact information, you can also view the Kammute page on our site.

Current projects

Expand the following projects below.


PROJECT SCOPE

The City of Kamloops has contracted DW Builders to complete restoration work at St. Andrews on the Square, returning the building to its pre-damage condition while also incorporating upgrades to improve accessibility, code compliance, and overall functionality.

This restoration work supports maintaining a tangible link to the past, anchoring Kamloops’ identity and historical continuity, while providing a useful, functional space for events and gatherings.

In May 2024, the facility–the oldest public building remaining in the city–sustained fire damage, with most of the impact limited to the exterior and attic, while the interior was primarily affected by smoke and firefighting water.

HOURS OF WORK

The work will occur Monday through Friday, from 7:00 am to 5:00 pm, from early October 2025 to February 2026.

Some evening or weekend work may be required.

PROJECT IMPACTS

Surrounding commercial and residential properties can expect noise and truck traffic.

Traffic impacts are not expected during this project.

UPDATE FOR DECEMBER 22

The majority of the project is complete. The contractor will return in the spring when conditions are suitable for planting and landscaping.


UPDATE FOR OCTOBER 7

Road closure:

  • Monarch Drive will be closed between Gleneagles Drive and McKinley Court from October 14–November 30. Follow signage and any direction from traffic control personnel on site.

Traffic pattern change:

  • Gleneagles Drive will be reduced to single lane alternating traffic when approaching either side of Monarch Drive. Follow signage and any direction from traffic control personnel on site.

Detours:

  • Vehicles can detour along Gleneagles Drive to Springhill Drive or via Gleneagles Drive to Summit Drive. Follow the posted signage.

Pedestrians:

  • The sidewalk on Monarch Drive, past Gleneagles Drive will be closed.
  • Pedestrians will be diverted to the opposite (south) side of the street. Temporary crosswalk lines will be painted across Monarch Drive (safely past the construction zone) to allow pedestrians to cross the road. Canada Post mailboxes will remain accessible. Traffic control personnel will assist pedestrians in the work area as needed.

No parking:

  • Parking will not be permitted around the intersection of Monarch Drive and Gleneagles Drive during bypass work. This will occur for 3-5 days. No parking signs will be posted during this work period.

Bus stop:

  • The bus stop on Gleneagles Drive north of Monarch Drive will be moved 50m north.

After hours:

  • When the crew is not on site, Monarch Drive will remain closed. The sidewalk in front of the construction zone will also remain closed to pedestrians. Traffic will flow as normal along Gleneagles Drive at Monarch Drive. There will be some thinning of the intersection at Monarch Drive to clear the construction zone. Follow cones and drive safely in the construction zone.

PROJECT SCOPE

The City of Kamloops has contracted Extreme Excavating Ltd. to perform sewer upgrades to the existing sanitary line between Monarch Drive and Waddington Drive, adjacent to Springhill Creek. The current sanitary line is aging and does not have enough capacity to meet the current demand.

The project will also include the creation of an access road at the corner of Gleneagles Drive and Monarch Drive, removal and replanting of trees and vegetation, reseeding disturbed areas outside of the road alignment, and upgrades to the walking path.

We are advising residents that this work is scheduled to begin in early October, with expected completion in December 2025.

Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some evening and weekend work required.

TRAFFIC IMPACTS

While some work will occur in the intersection of Monarch Drive and Gleneagles Drive, overall traffic impacts during this work will be minimal.

Please obey all traffic control personnel and signage when crews are in the area.

RESIDENT IMPACTS

Work will begin at Monarch Drive and end near Waddington Drive. The bulk of of the work will occur in the greenspace near Springhill Creek.

During the work, water service disruptions may occur. Impacted residents will receive advanced notification when any planned water shutoffs are scheduled.

Throughout the construction period, vibratory compaction equipment may be in use; therefore, any fragile items should be packaged or protected from damage due to vibration.

As this project location is in close proximity to streams, riparian areas, and wildlife, the City is abiding by an Environmental Management Plan that will help mitigate and minimize the potential for adverse environmental impacts, as well as provide best practices for how best to manage the work in this area.

PEDESTRIAN IMPACTS

For safety reasons, the green space and walking trail within construction zone will be closed for the duration of the construction project. Please obey all posted signage.

UPDATE FOR DECEMBER 22

The contractor will return in January (weather permitting) to continue work.

Once the building is complete, the mechanical apparatus for the pressure-reducing station will be installed. Once that is all complete, the final water connections will be done outside the building, connecting the higher-pressure zone to the lower-pressure zone (weather permitting).


UPDATE FOR JULY 10

On Friday, July 11, paving work will occur on Hillside Drive North and McGill Road just past Bunker Road.

Expect single lane alternating traffic and frequent temporary road closures to allow the movement of paving and construction equipment. Paving is expected to begin around 8:30 am on Friday.

To avoid commuting slowdowns due to moving paving equipment and single lane alternating traffic, it is recommended commuters travel along McGill Road away from the construction zone to access Summit Drive.


UPDATE FOR MAY 21
From May 23 until June 20, construction will move into the south side of Hillside Drive North. During this time, Hillside Drive North will be single lane alternating traffic moving up to Bunker Road. Traffic control personnel will be used to guide traffic.

On Saturday, June 21, there will be a temporary road closure on McGill Road just past the Bunker Road intersection. McGill Road will be accessible for local traffic only starting at the University Drive intersection. Bunker Road will be closed and traffic will exit McGill the same way it entered.

Further, the Bunker Road Recycling and Yard Waste Depot will be temporarily closed on June 21 due to the road closure.

After June 21, please expect single lane alternating traffic along within the corridor of McGill Road and Hillside Drive North as contractors pave and restore the boulevard. This work is expected to be completed by the end of July.

Note: All dates are approximate and may change based on weather and other factors.


PROJECT SCOPE

The City of Kamloops has contracted BA Dawson Blacktop Ltd. to install a watermain extension along Hillside Drive connecting the 2088 pressure zone to the 1786 pressure zone through a pressure reducing valve station.

The result will be an upgrade to water servicing in the area and improvement of fire protection to enable development of high density residential and commercial lots.

HOURS OF WORK

We are advising impacted properties that work will begin in spring 2025, with expected completion in fall 2025.

Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some weekend work required.

IMPACTS

Throughout the project, water service disruptions may occur. Impacted properties will receive advanced notification when any planned water shutoffs are scheduled.

During construction, dust control measures will be in place, as heavy vibratory equipment will be used. Pack up fragile items to protect them from damage due to vibration. Expect heavy truck traffic and noise disruptions from construction equipment.

PROJECT UPDATE

All roadway works have been completed, with the only remaining aspect of the project being the achievement of whistle cessation. The project team is working with all partners to achieve this final milestone and will provide an update in 2026. Thank you for your patience and co-operation thus far!


UPDATE FOR AUGUST 28

Work is scheduled to recommence on Lorne Street next week. To accommodate this work, a closure and detour will be in place on 7th Avenue from Tuesday, September 2, through Saturday, September 6 while crews build, install, and weld rail panels.

Residents on 7th Avenue will continue to have access during construction, and accommodations will be made as needed.

In addition, on Saturday, September 2, traffic will be single lane alternating on Lorne Street to support the unloading of materials.


UPDATE FOR JULY 14

Acres Enterprises has demobilized from site for a brief pause until Monday, August 11.

When the project restarts, road closures will temporarily recommence while the remainder of the work is completed.

Asphalt prep, paving, and restoration, including signage installation, will begin August 14, with overall project completion expected in September.


UPDATE FOR JUNE 13

A closure is planned at 7th Avenue and Lorne Street for construction for the Lorne Street Rail Improvement project. The closure should last 3 days while the construction crew reshapes the existing subgrade around the rail track. As of now, this is scheduled for June 16-18, but is subject to change. Please continue to monitor this page for project updates.


PROJECT SCOPE

The City of Kamloops has contracted Acres Enterprises Ltd. to perform rail safety improvements at CN Rail crossings on Lorne Street to accommodate improved safety for pedestrians, cyclists, and motorists to support the future cessation of train whistles.

The project is partially grant funded by Transportation Canada’s Rail Safety Improvement Program and will include the following elements:

  • Upgraded rail crossing warning systems at 7th Avenue and 8th Avenue
  • Lane reconfiguration and raising of the existing road profile
  • Excavation and fill works
  • Installation of fencing
  • Milling and paving
  • Line painting

HOURS OF WORK

We are advising residents that work is scheduled to begin in spring 2025, with completion anticipated in fall 2025.

Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some weekend work required.

TRAFFIC IMPACTS

Traffic will be temporarily impacted within the construction zone, including road closures, detour routes, and single lane alternating traffic patterns.

Please plan accordingly and obey all signage and traffic control personnel.

RESIDENT IMPACTS

During construction, dust control measures will be in place, as heavy vibratory equipment will be used. Pack up fragile items to protect them from damage due to vibration.

Expect heavy truck traffic and noise disruptions from construction equipment.

PEDESTRIAN IMPACTS

During construction, sidewalk closures may be in effect. Please obey all signage when navigating the area.

UPDATE FOR DECEMBER 22

The contractor will return in January and will start tunnelling under Highway 1 for the connection from Hillside Drive to Sugarloaf Road. Simultaneously, crews will continue to work on installing the sewer pipe in the lower section of the project. This will include blasting and earthworks in addition to the pipe installation.


PROJECT SCOPE

The City of Kamloops has contracted Extreme Excavating to add approximately 6.4kms of 600mm diameter and 450mm diameter gravity sanitary mains from Sugarloaf Road to Mission Flats Road.

Construction is scheduled to occur Monday through Friday, 7:00 am–5:00 pm, with the possibility of some evening and weekend work required, until summer 2026.

PROPERTY IMPACTS

Throughout the project, water service disruptions may occur. Impacted properties will receive advanced notification when any planned water shutoffs are scheduled.

During construction, dust control measures will be in place, as heavy vibratory equipment will be used. Pack up fragile items to protect them from damage due to vibration. Expect heavy truck traffic and noise disruptions from construction equipment.

Upcoming Projects

Upcoming Projects


Past Projects

Provide a short summary of your question.

You have 150 characters left

Provide detailed information relating to your question.

You have 500 characters left

Select a respondent from the list that you would most like to answer your question.

Moderation Policy

These are the people that are listening and responding to your questions.

Community Engagement Team

{{ question.username }} asked

{{question.description}}

{{ answer.respondent.name }}
| Edited

Answer this question

Select the respondent who will be marked as answering the question

Provide the answer to the question. Answer can be saved as draft and published when complete.

No questions found

Contact Us

Have questions or want to learn more about a project, contact us below:

Contact Information
Website www.kamloops.ca
In writing

City of Kamloops, 7 Victoria Street West, Kamloops BC, V2C 1A2

Land Acknowledgement

The City of Kamloops acknowledges that we are located on Tk̓emlúps te Secwépemc territory, situated within the unceded ancestral lands of the Secwépemc Nation.

We honour and respect the people, the territory, and the land that houses our community.