Update for November 3

3 November 2023

With paving of Tranquille Road between Crestline Street and Aviation Way complete, crews will be line painting on Friday, November 3 (weather permitting). Access to and from residences and businesses within the work zone will be maintained; however, motorists will be restricted from crossing the centre line when it is freshly painted.

Starting the week of November 6, crews will be working behind the curb on the north and south sides of Tranquille Road, prepping for shallow utilities and upcoming pedestrian infrastructure. They will also ensure driveways within the work zone are prepped for winter use. Work continues at the new Fulton Field Park site located off Tranquille Road just north of Aviation Way.

Motorists are reminded that the construction zone remains 30 km/hr, effective 24 hours a day, seven days a week.

Crews will continue to work onsite until winter shutdown. Work will then resume in spring 2024, and will include:

  • Construction of the sidewalk and swale (north side of Tranquille Road)
  • Construction of the multi-use pathway (south side of Tranquille Road);
  • Landscaping (trees, irrigation, sod);
  • Lighting;
  • Restoration of driveways;
  • Fulton Field Park completion.