Weather permitting, crews will resume work on the Copperhead Drive Extension project starting the week of January 22.

January 22 through January 26 (7:00 am to 5:00 pm each day), crews will be rock hammering to remove rock for the road and deep utilities trench at the east end of the Copperhead Drive extension where it meets the road to the new Pineview Elementary School. Residents are advised that the noise level should be minimal and will be within the allowed limits.

The week of January 29, installation of the deep utilities (storm, sanitary and watermain) will commence in this area.

Residents are reminded that a number of the existing walking trails within this construction area remain inaccessible. Fencing and signage is in place. Residents are asked to respect the closures and choose alternate walking routes.