Update for October 28

28 October 2025

Due to unforeseen circumstances (including inclement weather), the concrete pouring schedule has shifted slightly. The pour will now occur on Wednesday, October 29 and Thursday, October 30 (weather dependent).

A couple of reminders:

  • The crew will begin pouring concrete on the north side of Tranquille Road at Crestline Street and move eastward to Downie Street. Crews will then switch to the south side of Tranquille Road and move westward from Downie Street to Crestline Street.
  • While concrete pouring takes place, street parking is permitted on side streets or at Crestline Community Garden (795 Crestline Street). Vehicles parked on Tranquille Road during concrete pouring hours on October 29 and 30 (7:00 am to 6:00 pm) will be towed.
    • In the evening, driveways will remain inaccessible. Vehicles may park on the south side of Tranquille Road overnight from 6:00 pm to 7:00 am. Vehicles parked overnight on the south side of Tranquille Road must be moved before 7:00 am the next morning or they will be towed.

Following the concrete pour, until November 6, driveways will remain inaccessible. Vehicles may continue to park on the south side of Tranquille Road (day and night).

Vehicles must NOT drive or park on any new driveway letdowns, curbs, and poured concrete under any circumstance during and following concrete pouring.

IMPORTANT: The concrete requires significant time to cure and driving over it will result damage in to the curb. Any damaged curb will need to be removed, and the driveway will need to be closed for an additional 10-12 days while new curbs are poured.

Thank you for your continued patience and flexibility as we work to complete this portion of the project in a timely fashion.