Update for September 16

16 September 2025

The contractor has identified Monday, September 22 as the concrete pour date for the Riverside Park Skating Facility project, with work taking place from 4:00 am until 10:00 pm.

The work will involve a high volume of concrete trucks accessing the site from both the east and west. As such, the following closures have been requested for until the end of concrete placement (ETA 5:00pm):

  • Sandman Centre Parking Lot:
    • Partial closure in effect until the end of the pour.
  • Uji Way Parking Lot:
    • Full closure in effect until the end of the pour.