Update for November 21

Extreme Excavating is currently preparing the construction site for winter shutdown. Crews are completing the installation of the new traffic signals at the intersection of Highland Road and Valleyview Drive. These signals will become operational later this year.

Crescent Drive (east and west) at Highland Road has been re-opened to traffic. Transit has returned to its regular routing on Highland Road. All bus stops are back in operation.

Extreme Excavating will return to the site in spring 2023 to complete any outstanding work for Phase 1 (Highland Road from HIghway 1 to Valleyview Drive) and to start Phase 2 work (Highland Road from Valleyview Drive to Valleyview Arena).

Outstanding landscape restoration of impacted properties and boulevards will take place in spring 2023.

Thank you to the local residents and businesses, as well as motorists, pedestrians and transit users travelling through the site, for your patience during this year’s Highland Road Upgrades project.