Fleetwood Avenue - Phase 2 - COMPLETE

This project is complete.

Project Scope

The City of Kamloops will be conducting utility and road works as well as pedestrian upgrades on Fleetwood Avenue between Holt Street and Desmond Street. We are advising residents in the area that this work is scheduled to begin March 14, weather depending, and will encompass the following scope of work:

  • water service replacements;        

  • water main replacements; 

  • new drainage infrastructure        

  • sanitary upgrades;

  • pedestrian sidewalk; and         

  • road reconstruction.

Restoration work on Fleetwood Avenue between Southill Street and Desmond Street (Phase 1) will also be started and completed this spring in conjunction with Phase 2 work. 

Resident Impacts

Throughout the construction period, vibratory compaction equipment will be in use; therefore, any fragile items should be packaged or protected from damage due to vibration. There may also be noise disruption due to equipment on site. 

In order to perform utility works, there will be frequent water interruptions. Expect intermittent water shutdowns of three hours or less during this portion of the project. When possible we will inform residents daily of longer duration water shutdowns in excess of three hours. We recommend that residents store a quantity of water for use during the longer duration periods.

Garbage collection will not be affected.

Hours of Work

Work will begin on March 14 and is expected to be complete in August. Construction is scheduled to occur Monday–Friday, 7:00 am–4:00 pm. Some evening or weekend work may be required.

Traffic & Transit Impacts

Fleetwood Avenue, between Holt Street and Desmond Street, will be closed for the duration of the project, with the exception of local traffic. 

Driveway access to residents will be temporarily restricted at times during construction. Residents are advised that off-street parking may not be accessible at times during construction and to plan ahead by moving vehicles to adjacent streets before work commences Monday to Friday. On-street parking is not permitted during working hours on weekdays.

Effective March 7, transit Route 2 will operate on Parkcrest Avenue between Southill Street and Holt Street. Temporary bus stops will be in place as indicated on the map below. Visit NextRide or BCTransit.com/Kamloops for further details. 

Please obey all traffic control personnel and signage when driving in the vicinity of the construction. 


Share on Facebook Share on Twitter Share on Linkedin Email this link